Rail to Reston Hitting the Homestretch

The Silver Line's first phase is on schedule to take riders to Wiehle Avenue by December 2013 and a construction contract for Phase 2 should be awarded in May.

The first phase of the Silver Line is 89 percent complete and is on schedule to be taking Metro passengers to Reston Reston in December 2013, officials confirmed this week.

Mark Canale, Dulles Rail Project Manager for the Fairfax County Department of Transportation, said construction on the first phase is on track.

During a Tuesday meeting of Fairfax County’s commission for the Phase 1 Transportation Improvement District, Canale said 98 percent of tracks for the extension from East Falls Church to Wiehle Avenue have been laid down.

Find out what's happening in Restonwith free, real-time updates from Patch.

Some track work remains, as well as construction on garages and stations, but Canale said service in December was looking very likely.

The West Falls Church rail yard is expected to be complete around the same time the line is scheduled to become operational, Canale said. In the event the rail yard isn’t ready for storage, Silver Line cars will be stored elsewhere in the Metro System, he said, assuring officials it would not affect service.

Find out what's happening in Restonwith free, real-time updates from Patch.

“We’re currently expecting to come in within the authorized budget of $2.9 billion,” he said. To date, about $2.1 billion has been spent, he said.

The Washington Metropolitan Area Transit Authority (WMATA) has been performing tests on the tracks the past few weeks, including running cars through tunnels. Tests on the tracks will continue through completion.

Officials have said construction will be complete in August and testing for the Silver Line will begin shortly after in anticipation of the December opening.

They have not yet chosen a specific opening date.

Phase 2

Transportation officials said they hope to have the construction contract awarded to a company sometime in May 2013.

The $3 billion extension from Reston to Dulles International Airport and into Ashburn is tentatively scheduled to open for riders in late 2018, with major construction completion in the summer of that year.

Bulova wanted to know when officials and residents could expect to see some groundbreaking on the final phase.

Canale said if a developer for the project is found on time and gets working quickly, riders could movement on construction between December 2013 and the summer of 2014.

The official projected cost of the project will be revealed after April 19, when bids on for construction are due back from contractors.

More:

Biking to the Wiehle Avenue Rail Station

Hudgins Asks Supervisors for $2.2 for Reston buses

 


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here